November 20, 1997
Tasks & Time Line
for Completion of Project CHIO
Draft
The following provides a draft list of tasks to be accomplished and time line for completion of the NEH sponsored Project CHIO Access. This project began in Fall 1995 and has a completion deadline of February 28, 1998. The major focus between November 20 and February 28 fall into two major areas: 1) revision and preparation of the CIMI Profile; 2) completing project report on the entire 2-year project.
Profile Revision
Tasks (and Lead Person):
1. Preliminary Revision of Profile (Moen)
2. Additional Implementation Guidance for Profile:
3. Z39.50 Working Group Meeting, Orlando, 1/19-1/20/98
4. Finalize CIMI Profile, Release 1.0 (Moen)
Timeline:
11/20-12/15:
12/5:
12/15:
12/15-1/10:
1/10-1/17:
1/18:
1/19-1/20: Z39.50 Working Group Meeting, Orlando
1/21-2/1:
2/1-2/15:
2/15:
Project Report
Tasks (and Lead Person):
Outline of Final Project Report (Perkins)
Gathering of Relevant Documents (Moen & Perkins)
Moving all Moen's Electronic Project Documents to CIMI Website (Moen, Stevenson)
Organizing Project Documents on Website (Stevenson)
15 Page Draft of Report Related to Z39.50 Profile Development/Interoperability Testbed (Moen)
Additional Information to be included in Report (Perkins & Moen)
Review of Complete Draft Report (Who should do review?)
Prepare Final Version of Report (Need to discuss the role of CIMI HQ in preparation of Report and Associated documentation for the report)
Timeline:
12/1-12/15:
12/15-1/1:
1/1-1/31:
2/1-2/7:
2/7-2/15
2/15: