| Time
Period |
Activities |
Status |
|
By September
30, 2000
|
|
|
| |
Announce NISO will take on this work – widespread publicity |
Completed |
| |
Begin identifying potential committee members |
Completed |
| |
Work out a detailed schedule of activities |
|
| By October 31,
2000 |
|
|
| |
Confirm all committee members |
Completed |
| |
Set up public (and private?) listservs and website presence |
Completed |
| |
Establish date for first
meeting (two days) in November; potential dates
for first meeting: |
Completed |
| By November 30,
2000 |
|
|
| |
Prepare agenda and work items for committee |
|
| |
Review Bath Profile and other relevant profiles |
|
| |
Committee members identify any additional requirements for their
constituencies not addressed by Bath Profile |
|
| |
Committee members identify any objections to specifications contained in
Bath Profile |
|
| |
Hold first committee meeting in Dallas, TX |
|
| |
Agreement on tentative schedule for completion of work |
|
| By December 31,
2000 |
|
|
| |
Committee members continue to identify any additional requirements for
their constituencies not addressed by Bath Profile |
|
| |
Committee members continue to identify any objections to specifications
contained in Bath Profile |
|
| By January 31, 2001 |
|
|
| |
Hold second committee meeting in conjunction with ALA Midwinter Meeting
in Washington, DC (Jan. 12-17) – most likely right before ALA Midwinter |
|
| |
Hold public hearing during ALA Midwinter meeting on the national profile |
|
| |
First Draft of National Profile ready for review by committee members |
|
| By February 28,
2001 |
|
|
| |
Review and revision of First Draft of National Profile |
|
| |
Release of public draft of National Profile for 30-day comment period
prior to balloting |
|
| By March 31,
2001 |
|
|
| |
Compile comments from public review of draft national profile |
|
| |
Revise draft profile and prepare for ballot by NISO |
|
| |
Committee meeting if necessary to work out final ballot draft |
|
| By April 30,
2001 |
|
|
| |
45-day ballot period underway (preferably by April 15) |
|
| By May 31, 2001
|
|
|
| |
Ballot period over |
|
| |
Resolution of negative votes and comments |
|
| |
Committee meeting if necessary to resolve votes and comments |
|
| By June 30,
2001 |
|
|
| |
Z39.50 National Profile for Library Applications approved as an American
National Standard |
|